Projects - Zinc flotation at Gamsberg Zinc Mine
Novatec SA Projects
Our team knows no boundaries: we can provide completed solutions to automate industrial processes across continents. Below is a few of the projects worked on thus far.

Novatec SA Projects Projects

Project Case Study Novatec SA - Small Projects

31 May 2022

No matter the size of a project we are always up for a challenge. Here are just some of the small projects Novatec SA has worked on.


1. MULTOTEC KENDAL INSPECTION - PLC WIRING AND REMOTE IO

Multotec requested that we help them with a bit of maintenance.

 The Scope of work consisted out of the following and we managed to neaten PLC panel wiring without disconnecting any cables.

 Install new lights and new fire door into e-house

Fix and neaten PLC panel wiring

Install cable tags for PLC panels

Cleaning field RIO's

Close holes in field RIO's

2. GAMSBERG ZINC CLEANER FLOTATION CIRCUIT EXPANSION - ELECTRICAL, CONTROL AND INSTRUMENTATION DESIGN

For a duration of 5 months our Engineers have been hard at work to Complete Electrical, Control and Instrumentation detailed designs for the cleaner Circuit Upgrade.

Zinc flotation is one of only three phase 1 upgrades before a complete second concentrator is to be built at Gamsberg Zinc Mine.

3. MEDUPI UNIT 1 - AUTOMATION ENGINEERING FOR DUST HANDLING PLANT

In July 2020 Novatec SA assisted with the completion and commissioning of Medupi Unit 1 Dust Handling Plant, for a duration of two months.

Our Junior Automation Engineer Scott Anderson, worked hand in hand with ELB Construction to make sure the set goals get achieved.

Back to projects page